WithFunded › Working capital › Texas › Plano
Working capital for Plano contractors
Plano makes the general contractor and every subcontractor on a permit register with the city, at $100 a year for general, roofing, concrete, and irrigation contractors, collects at least 65% of the building permit fee when you apply, holds refundable recycling deposits of up to $11,250 on larger projects, and records most liens through the Collin County Clerk.
By the WithFunded team · Reviewed by Angelo Orru Neto, CFP®, MSc, Managing Partner · Published November 19, 2026 · Plano rules checked November 19, 2026
Guides by trade
- General contractorsBest for the gap between pay applications: business line of credit
- Electrical contractorsBest for gear and wire bought ahead of the draw: business line of credit
- Plumbing contractorsBest for the gap from rough-in to trim-out: business line of credit
- HVAC contractorsBest for equipment bought before the draw: business line of credit
- Roofing contractorsBest for materials before the final check: business line of credit
- Concrete contractorsBest for ready-mix and payroll between pours: business line of credit
- Excavation contractorsBest for fuel, repairs, and payroll: business line of credit
- Landscaping companiesBest for the spring ramp-up: business line of credit
- Remodeling contractorsBest for the gap between milestones: business line of credit
See what your Plano business qualifies for
Answer a few questions in about 2 minutes and get matched to your best-fit option. Zero upfront fees. Checking won't impact your credit.
See what I qualify for →Permits, liens, and city work in Plano
Plano's Building Inspections Department, at 1520 K Ave., issues building and trade permits, and a building permit is issued only once the general contractor and its subcontractors are registered and validated on it. Registered contractors schedule inspections online through eTRAKiT, and work in the City right-of-way needs a separate Engineering Department permit. (City of Plano Development Handbook (Feb. 2026))
Where liens are recorded
Most of Plano is in Collin County, where mechanics liens are recorded with the Collin County Clerk at 2300 Bloomdale Road, Suite 2106, in McKinney, for $25 for the first page and $4 for each additional page. Property in the part of Plano that lies in Denton County is recorded with the Denton County Clerk. (Collin County Clerk land recording fees)
Working for the city
The City of Plano's purchasing terms, revised in March 2026, say the City pays under the Texas Prompt Payment Act unless a contract says otherwise, once it receives a properly executed invoice. Invoices go to the City's Accounting Department and must carry the City's purchase order number. (City of Plano General Terms and Conditions (Mar. 2026))
Plano runs no small, minority, or local business certification of its own; its Purchasing page points firms to the Texas Comptroller's HUB program. City bid and quote opportunities over $3,000 are posted on the City's IonWave system, where vendor registration is free. (City of Plano Purchasing, suppliers)
Weather that moves the work
On June 13, 2012, storms pummeled parts of Dallas, Collin, and Fannin counties with hail as large as softballs (4.25 inches), and early estimates put the damage at about $900 million, one of the costliest hail storms in Texas, according to the National Weather Service in Fort Worth. (National Weather Service Fort Worth)
Other Plano rules worth knowing
You pay at least 65% of the building permit fee plus the plan review fee when you apply, and the balance before the permit is issued. Any job valued at $10,000 or more must list a solid waste removal subcontractor on the application. (City of Plano permit application submittal requirements)
A permit expires after 180 days without work or an inspection, and 10 working days after it expires the responsible contractor's registration is put on hold until the permit is reactivated; renewing an expired permit within six months, with no plan changes, costs half the original building permit fee. (City of Plano renewal of expired permit process)
New construction and demolition of 5,000 square feet or more, and alterations or finish-outs of 10,000 square feet or more, require a recycling deposit of $0.25, $0.20, or $0.15 per square foot, up to $11,250. It is refunded by diversion rate if you file the refund request with weight tickets within 180 days of completion, and only Republic Services may set trash containers in Plano. (City of Plano C&D Recycling Deposit Program)
The fee schedule effective January 2, 2026 charges $85 for a simple residential electrical, plumbing, or mechanical permit ($100 commercial without plans, $125 with plans), $150 per trade for a same-day inspection, and re-inspection fees of $75 to $150 that must be paid before any final inspection is scheduled. (City of Plano Building Inspections fee schedule (Jan. 2026))
On development projects, the City collects an inspection fee of 4% of the approved unit cost breakdown of the public improvements before it releases the engineering plans for construction. Plano charges no impact fees. (City of Plano Development Handbook (Feb. 2026))
On one City trail project, the Preston Ridge Trail Connector (Project No. 6173), the City's December 2021 monthly pay request held back 5% retainage from the contractor's earnings, according to the reimbursement request Plano sent Collin County; other City contracts may set different terms. (City of Plano reimbursement request to Collin County (2022))
For property in the Denton County part of Plano, the Denton County Clerk charges $25 for the first page, plus a required $4 recording information page and $4 for each additional page. (Denton County Clerk recording fees)
Texas payment rules that apply in Plano
Texas payment rules at a glance
- Private owner pays prime
- Within 35 days of a payment request
- Contractor pays subs
- Within 7 days of being paid; 1.5% a month if late
- Owner's statutory holdback
- 10% of the contract price until 30 days after completion
- Public jobs
- Overdue on day 31; subs paid within 10 days
- Commercial lien deadline
- 15th day of the 4th month after your work ends
- Fast-funding law
- Yes: registration and cost disclosure for merchant cash advances
On private jobs, the owner must pay a contractor's properly submitted written payment request within 35 days of receiving it, and each contractor and subcontractor must pay its own subs their share within 7 days of being paid. Late amounts earn 1.5% interest per month. A contract for a single-family home may extend the owner's deadline to 60 days. (Tex. Prop. Code §§ 28.002, 28.004, 28.006)
Since September 1, 2025, Texas has regulated merchant cash advances and other commercial sales-based financing. Providers and brokers must register with the Office of Consumer Credit Commissioner by December 31, 2026; offers under $1 million must disclose in writing the finance charge, total repayment, estimated term, payments, and broker compensation; confession-of-judgment clauses are void; and automatic debits are banned unless the provider holds a perfected first-priority security interest. (Tex. Fin. Code ch. 398 (H.B. 700, 2025))
See working capital for Texas contractors for retainage, lien deadlines, and public-job rules in full.
Small business lending in Plano
Plano is in the Dallas-Plano-Irving metropolitan division, which had 183,300 jobs in mining, logging, and construction in September 2026 (preliminary, not seasonally adjusted), up 2.1% from 179,600 a year earlier; BLS publishes no construction-only series for this division. (U.S. Bureau of Labor Statistics)
The SBA's Dallas/Fort Worth District Office, which serves 72 counties in northeastern Texas, covers Plano and can point you to lenders and free counseling. (SBA)
Frequently asked questions
- Do I have to register with the City of Plano to pull permits?
- Yes. A permit is issued only once the general contractor and its subcontractors are registered and validated on it. General, concrete, roofing, and other building trades register as general contractors for $100 a year, irrigation contractors also pay $100, and electrical, mechanical, and plumbing contractors register their Texas licenses and insurance. Homeowners can pull permits for their own homes without registering.
- How fast does the City of Plano pay its contractors?
- Plano's purchasing terms say it pays under the Texas Prompt Payment Act unless the contract says otherwise, which generally makes a payment overdue on the 31st day after the later of delivery, completion, or the invoice. On one City trail project, the December 2021 pay request held 5% retainage.
- Where do I file a mechanic's lien on Plano property?
- For most of Plano, with the Collin County Clerk at 2300 Bloomdale Road in McKinney, at $25 for the first page and $4 for each additional page. Property in Plano's Denton County area is recorded with the Denton County Clerk, which charges $25 for the first page plus a required $4 recording information page and $4 for each additional page.
Get matched to working capital
Answer a few questions in about 2 minutes and get matched to your best-fit option. Zero upfront fees. Checking won't impact your credit.
See what I qualify for →Sources
- City of Plano Development Handbook (Feb. 2026)
- Collin County Clerk land recording fees
- City of Plano General Terms and Conditions (Mar. 2026)
- City of Plano Purchasing, suppliers
- National Weather Service Fort Worth
- City of Plano permit application submittal requirements
- City of Plano renewal of expired permit process
- City of Plano C&D Recycling Deposit Program
- City of Plano Building Inspections fee schedule (Jan. 2026)
- City of Plano reimbursement request to Collin County (2022)
- Denton County Clerk recording fees
- U.S. Bureau of Labor Statistics
- SBA office serving Plano
- Tex. Prop. Code §§ 28.002, 28.004, 28.006
- Tex. Fin. Code ch. 398 (H.B. 700, 2025)
Other Texas cities
Not legal advice. This page summarizes Texas statutes as they read on November 19, 2026, for general information. Deadlines depend on the contract, the type of project, and any later amendments. Confirm a deadline with a Texas construction attorney before you rely on it.
Disclaimer. WithFunded and Big Think Capital are a financing marketplace; we are not the direct lender and do not guarantee funding, approval, rates, or terms. Everything on this page is a representative example only — not an offer or a commitment to lend, and not financial advice. Actual rates, fees, payments, and terms are set by the funding lender and depend on your business, credit, and the product. Where required by state law, the lender provides cost-of-financing disclosures before any agreement is signed.