WithFunded › Working capital › California
Working capital for California contractors
California law sets firm payment clocks for contractors: a private owner has 30 days to pay an undisputed progress payment, subcontractors must be paid within 7 days, retention on private contracts signed since 2026 is capped at 5%, and a home-improvement down payment is capped at $1,000 or 10%.
By the WithFunded team · Reviewed by Angelo Orru Neto, CFP®, MSc, Managing Partner · Published November 19, 2026 · California law checked November 19, 2026
California payment rules at a glance
- Private owner pays prime
- Within 30 days of a written payment demand
- Prime pays subs
- Within 7 days of each progress payment
- Private retention
- Capped at 5% on contracts from January 1, 2026
- Public retention
- 5% cap; released within 60 days of completion
- Home-improvement deposit
- The lesser of $1,000 or 10%
- Fast-funding disclosure law
- Yes: cost and APR disclosure on offers up to $500,000
Guides by trade
- General contractorsBest for the gap between pay applications: business line of credit
- Electrical contractorsBest for gear and wire bought ahead of the draw: business line of credit
- Plumbing contractorsBest for the gap from rough-in to trim-out: business line of credit
- HVAC contractorsBest for equipment bought before the draw: business line of credit
- Roofing contractorsBest for materials before the final check: business line of credit
- Concrete contractorsBest for ready-mix and payroll between pours: business line of credit
- Excavation contractorsBest for fuel, repairs, and payroll: business line of credit
- Landscaping companiesBest for the spring ramp-up: business line of credit
- Remodeling contractorsBest for the gap between milestones: business line of credit
Guides by city
- BakersfieldKern County
- FresnoFresno County
- Long BeachLos Angeles County
- Los AngelesLos Angeles County
- OaklandAlameda County
- SacramentoSacramento County
- San DiegoSan Diego County
- San FranciscoSan Francisco, a consolidated city and county
- San JoseSanta Clara County
See what your California business qualifies for
Answer a few questions in about 2 minutes and get matched to your best-fit option. Zero upfront fees. Checking won't impact your credit.
See what I qualify for →Retainage
For private contracts signed on or after January 1, 2026, retention can't be more than 5% of any payment or of the contract price, and a subcontract can't hold back a higher percentage than the prime contract; non-mixed-use residential projects of four stories or less are exempt. The owner must pay retention within 45 days after completion, the prime must pass each sub its share within 10 days of receiving it, and late retention carries a 2% a month penalty. (Cal. Civ. Code §§ 8811, 8812, 8814, 8818)
On public works, retention is capped at 5% of each payment and of the contract price, unless the agency finds before bidding that the project is substantially complex. The agency must release retention within 60 days after completion, the prime must pay subs their share within 7 days of receiving it, and late retention carries a 2% a month charge. (Cal. Pub. Cont. Code §§ 7201, 7107)
Prompt payment
Unless the contract says otherwise in writing, a private owner must pay an undisputed progress payment within 30 days after the prime contractor's written payment demand, and a prime or sub must pay its subcontractors within 7 days after receiving each progress payment. Late payers owe a 2% a month penalty, and a good-faith dispute lets the payer hold back no more than 150% of the disputed amount. (Cal. Civ. Code § 8800; Cal. Bus. & Prof. Code § 7108.5)
A state or local agency that doesn't pay an undisputed, properly submitted progress payment within 30 days owes interest at the legal rate of 10% a year, and it must return an improper request within 7 days with written reasons. Primes must pay subcontractors within 7 days after receiving each progress payment, with a 2% a month penalty for paying late. (Cal. Pub. Cont. Code §§ 20104.50, 10261.5, 10262)
Lien rights and deadlines
A direct contractor must record a mechanics lien after finishing its contract and before the earlier of 90 days after the whole project is complete or 60 days after the owner records a notice of completion or cessation. The lien expires unless a lawsuit to enforce it is filed within 90 days after recording. (Cal. Civ. Code §§ 8412, 8460)
Subcontractors and suppliers must serve a preliminary notice on the owner, prime contractor, and construction lender within 20 days after first furnishing work, and must record any lien before the earlier of 90 days after completion or 30 days after a recorded notice of completion or cessation. On public jobs, unpaid subs and suppliers use stop payment notices and payment-bond claims instead. (Cal. Civ. Code §§ 8204, 8414, 9100)
An owner who lives in the home (four or fewer units) isn't required to mail you a copy of a recorded notice of completion, so the shorter 60-day (prime) or 30-day (sub) lien deadline can start without you being told. Home-improvement contracts must include a Mechanics Lien Warning, and the homeowner can withhold payment until you provide lien releases. (Cal. Civ. Code § 8190(d); Cal. Bus. & Prof. Code § 7159.5(a)(6))
Home-improvement contracts
On home-improvement contracts over $500, the down payment can't exceed $1,000 or 10% of the contract price, whichever is less, and after that you can't request or accept payment that exceeds the value of work done or materials delivered under the written payment schedule. Contractors with a CSLB-approved bond or joint control are exempt from these limits. (Cal. Bus. & Prof. Code § 7159.5(a)(3)–(5), (a)(8))
Most home-improvement contracts must give the buyer three business days to cancel, or five if the buyer is 65 or older, unless the deal was negotiated at your place of business, and you must refund everything paid within 10 days of a cancellation. Taking too large a down payment or collecting ahead of the work is a misdemeanor. (Cal. Bus. & Prof. Code §§ 7159(e)(6), 7159.5(b))
A contractor generally can't offer or give a discount meant to offset an insurance deductible unless the insurer has already set the claim amount and the work follows it, and may not pay insurance agents or adjusters for referrals. Negotiating a homeowner's claim for pay requires a public adjuster license, and repair contracts after a declared emergency carry a seven-business-day right to cancel. (Cal. Penal Code § 551; Cal. Ins. Code § 15006)
Rules on fast business funding
Providers of business financing offers of $500,000 or less, including merchant cash advances, factoring, loans, and leases, must give you a signed disclosure before closing showing the amount funded, total cost, term, payment schedule, prepayment policy, and an APR, and since January 1, 2026 they must state the APR whenever they quote a price. Under AB 2116, signed September 30, 2026, providers and brokers will need a state license from July 1, 2028. (Cal. Fin. Code §§ 22800–22807; AB 2116 (2026))
Small business lending in California
California has 4,340,784 small businesses employing 7,595,688 people, 47.4% of the state's employees (2022 data). (SBA Office of Advocacy, 2025 California profile)
The state has about 321,800 small construction businesses, and its 83,428 small construction employers employ 80.5% of California's construction workers (2022 data). (SBA Office of Advocacy, 2025 California profile)
SBA loans, including CAPLines working capital lines, are made by private lenders and guaranteed by the U.S. Small Business Administration. The SBA serves California through six district offices, in Fresno, Los Angeles, Santa Ana (Orange County and the Inland Empire), Citrus Heights (Sacramento), San Diego, and San Francisco, (SBA), which can point you to lenders and free counseling. See our SBA loan guide for current rate caps.
Frequently asked questions
- How long does a California owner have to pay a contractor?
- Unless the contract says otherwise in writing, a private owner must pay an undisputed progress payment within 30 days after the contractor's written demand, with a 2% a month penalty if late. State and local agencies have 30 days to pay a proper payment request and owe interest at 10% a year after that.
- How fast must a California contractor pay subcontractors?
- Within 7 days after receiving each progress payment, unless agreed otherwise in writing, with a 2% a month penalty for paying late. Retention must reach subs within 10 days of the prime receiving it on private jobs and within 7 days on public jobs.
- How much retention can be held in California?
- On private contracts signed on or after January 1, 2026, retention is capped at 5% of each payment and of the contract price, except on non-mixed-use residential projects of four stories or less, and the owner must release it within 45 days after completion. On public works the cap is 5% unless the agency found the project substantially complex before bidding, with release within 60 days after completion.
- How much of a deposit can a California contractor take on a home improvement job?
- On contracts over $500, the down payment may not exceed $1,000 or 10% of the contract price, whichever is less, and later payments may not exceed the value of the work done or materials delivered. Contractors with a CSLB-approved bond or joint control arrangement are exempt from those limits.
- Can a California homeowner cancel a remodeling or roofing contract?
- Most home-improvement contracts give the buyer three business days to cancel, or five if the buyer is 65 or older, unless the deal was negotiated at your place of business. You must refund everything paid within 10 days of a cancellation.
- Can a California roofer cover a homeowner's insurance deductible?
- Generally no. Offering or giving a discount meant to offset a deductible is a crime unless the insurer has already set the claim amount and the work follows it, and negotiating the claim for pay requires a public adjuster license. Talk to a lawyer before offering any deductible-related discount.
- Do California lien deadlines differ for home jobs?
- The deadlines are the same, but an owner who lives in the home (four or fewer units) does not have to send you a copy of a recorded notice of completion, so the shorter 60-day (prime) or 30-day (sub) deadline can start without notice. Check the county recorder after you finish.
Get matched to working capital
Answer a few questions in about 2 minutes and get matched to your best-fit option. Zero upfront fees. Checking won't impact your credit.
See what I qualify for →Sources
- Cal. Civ. Code §§ 8811, 8812, 8814, 8818
- Cal. Pub. Cont. Code §§ 7201, 7107
- Cal. Civ. Code § 8800; Cal. Bus. & Prof. Code § 7108.5
- Cal. Pub. Cont. Code §§ 20104.50, 10261.5, 10262
- Cal. Civ. Code §§ 8412, 8460
- Cal. Civ. Code §§ 8204, 8414, 9100
- Cal. Civ. Code § 8190(d); Cal. Bus. & Prof. Code § 7159.5(a)(6)
- Cal. Bus. & Prof. Code § 7159.5(a)(3)–(5), (a)(8)
- Cal. Bus. & Prof. Code §§ 7159(e)(6), 7159.5(b)
- Cal. Penal Code § 551; Cal. Ins. Code § 15006
- Cal. Fin. Code §§ 22800–22807; AB 2116 (2026)
- SBA Office of Advocacy, 2025 California profile
- SBA district offices serving California
Other states
Not legal advice. This page summarizes California statutes as they read on November 19, 2026, for general information. Deadlines depend on the contract, the type of project, and any later amendments. Confirm a deadline with a California construction attorney before you rely on it.
Disclaimer. WithFunded and Big Think Capital are a financing marketplace; we are not the direct lender and do not guarantee funding, approval, rates, or terms. Everything on this page is a representative example only — not an offer or a commitment to lend, and not financial advice. Actual rates, fees, payments, and terms are set by the funding lender and depend on your business, credit, and the product. Where required by state law, the lender provides cost-of-financing disclosures before any agreement is signed.