Working capital for Massachusetts contractors
Massachusetts' prompt-pay and retainage laws cover private projects whose prime contract is $3 million or more, giving owners 15 days to approve a pay application and 45 days to pay it and capping retainage at 5%; home-improvement deposits are capped at one-third of the price, and lien rights start with a notice of contract recorded at the registry of deeds.
By the WithFunded team · Reviewed by Angelo Orru Neto, CFP®, MSc, Managing Partner · Published November 19, 2026 · Massachusetts law checked November 19, 2026
Massachusetts payment rules at a glance
- Owner approves and pays
- 15 days to approve, then 45 days to pay (private jobs of $3 million or more)
- Contractor pays subs
- First-tier subs: approved within 22 days, paid 45 days later ($3 million+ jobs)
- Private retainage
- Capped at 5% on jobs of $3 million or more; no cap on smaller jobs
- Lien deadline
- Notice of contract by 90 days after last work, or 60 days after a substantial-completion notice if sooner
- Home-improvement deposit
- Up to one-third of the price, or the cost of special-order materials if more
- Fast-funding disclosure law
- None enacted
Guides by trade
- General contractorsBest for the gap between pay applications: business line of credit
- Electrical contractorsBest for gear and wire bought ahead of the draw: business line of credit
- Plumbing contractorsBest for the gap from rough-in to trim-out: business line of credit
- HVAC contractorsBest for equipment bought before the draw: business line of credit
- Roofing contractorsBest for materials before the final check: business line of credit
- Concrete contractorsBest for ready-mix and payroll between pours: business line of credit
- Excavation contractorsBest for fuel, repairs, and payroll: business line of credit
- Landscaping companiesBest for the spring ramp-up: business line of credit
- Remodeling contractorsBest for the gap between milestones: business line of credit
Guides by city
- BostonSuffolk County
See what your Massachusetts business qualifies for
Answer a few questions in about 2 minutes and get matched to your best-fit option. Zero upfront fees. Checking won't impact your credit.
See what I qualify for →Retainage
On private projects whose prime contract is $3 million or more, other than 1–4 unit homes, retainage may not exceed 5% of any progress payment. Starting 60 days after substantial completion, each contractor can apply for its retainage, and the application must be paid within 30 days, plus 7 more days at each tier below; only limited amounts for unfinished work, missing closeout documents, and claims may be withheld. Smaller private jobs have no statutory cap. (M.G.L. c. 149, § 29F)
On public building contracts, the state or local awarding authority may keep a retention of no more than 5% of each approved monthly payment, apart from amounts held for its own claims and subs' direct-payment demands, and within 65 days after the contractor substantially completes the work it must pay the entire balance, less its estimated claims and the cost of unfinished or unsatisfactory items. Public roads, bridges, sewers, water mains and other public works also cap retention at 5% of each periodic payment. (M.G.L. c. 30, §§ 39K, 39G)
Prompt payment
On private projects whose prime contract is $3 million or more, other than 1–4 unit homes, the owner has at most 15 days to approve or reject a pay application and 45 days after approval to pay it, and each tier below may take only 7 more days than the tier above to approve. An application not rejected in writing before payment is due counts as approved, pay-when-paid clauses are void unless you failed to perform or the owner is insolvent, and a contract generally cannot make you keep working once an approved payment is more than 30 days late. The law sets no interest rate, and smaller private jobs follow the contract. (M.G.L. c. 149, § 29E)
Cities, towns, and other local public bodies must pay a contractor's monthly estimate on public building and public works contracts within 15 days of receiving it, and the state within 30 days, with interest at 3 percentage points above the Federal Reserve Bank of Boston's rediscount rate if late. On competitively bid public jobs, the general contractor must pay each sub its share 'forthwith' after being paid, and an unpaid sub can demand direct payment from the public owner. (M.G.L. c. 30, §§ 39F, 39G, 39K)
Lien rights and deadlines
A contractor with a written contract must record a notice of contract at the registry of deeds by the earliest of 60 days after a notice of substantial completion is recorded, 90 days after a notice of termination, or 90 days after the last work on the job. It must then record a statement of the amount due within 90 days after the substantial-completion notice or 120 days after termination or last work, whichever comes first, sue within 90 days after recording that statement, and record an attested copy of the complaint within 30 days of suing. (M.G.L. c. 254, §§ 2, 5, 8, 11)
Subcontractors and suppliers with a written contract record their own notice of contract on the same deadlines, which run from the general contractor's notices and the last work on the whole project, not from when the sub finished, and must give the owner actual notice of the filing. A sub's lien cannot exceed what is due or will become due under the general contract when it notifies the owner, and a lower-tier sub or supplier that does not send the general contractor a notice of identification by certified mail within 30 days of starting work is limited to what is due or will become due on the first-tier subcontract. (M.G.L. c. 254, §§ 4, 8)
Massachusetts sets no separate lien deadlines for homes: a contractor on a home job records a notice of contract and a statement of the amount due on the same schedule as any other job. A contractor's lien rests on a written contract with the owner, which the Home Improvement Contractor law already requires for home improvement jobs over $1,000. (M.G.L. c. 254, §§ 2, 8; c. 142A, § 2)
Home-improvement contracts
On a home improvement contract with the owner of an existing owner-occupied 1–4 unit home, a deposit required before work starts may not exceed one-third of the total contract price or, if greater, the actual cost of special-order or custom materials that must be ordered in advance. Final payment may not be demanded until the work is completed to the satisfaction of both parties. (M.G.L. c. 142A, § 2(a)(6))
Home improvement contracts over $1,000 must be written and signed, with the contractor's registration number, start and completion dates, a detailed description of the work and materials, the total price, and a payment schedule in dollars, and work may not begin until the owner has a signed copy. A contract signed away from the contractor's place of business can be canceled until midnight of the third business day, with payments refunded within 10 business days. (M.G.L. c. 142A, § 2; c. 93, § 48)
No Massachusetts statute singles out roofing deductibles, but a contractor who negotiates or settles a homeowner's insurance claim for pay is acting as a public insurance adjuster and needs that license, with fines of up to $10,000 for unlicensed adjusting. Submitting an estimate or invoice padded to hide a waived deductible can be prosecuted as insurance fraud, punishable by up to 5 years in state prison. (M.G.L. c. 175, §§ 162, 172; c. 266, § 111A)
Rules on fast business funding
Massachusetts has not enacted a commercial financing disclosure or merchant cash advance law as of November 2026, and the state's Truth in Lending Act does not apply to credit extended primarily for business, commercial, or agricultural purposes, so it gives a business borrower no required cost disclosure. (M.G.L. c. 140D, § 2(a); no commercial financing disclosure law enacted)
Small business lending in Massachusetts
Massachusetts has 756,096 small businesses employing 1,516,837 people, 44.7% of the state's employees (2022 data). (SBA Office of Advocacy, 2025 Massachusetts profile)
The SBA counts 80,114 small construction businesses in Massachusetts, 21,072 of them with employees, and small firms employ 84.3% of the state's construction workers (2022 data). (SBA Office of Advocacy, 2025 Massachusetts profile)
SBA loans, including CAPLines working capital lines, are made by private lenders and guaranteed by the U.S. Small Business Administration. The SBA serves Massachusetts through its Massachusetts District Office, which covers the whole state, (SBA), which can point you to lenders and free counseling. See our SBA loan guide for current rate caps.
Frequently asked questions
- How long does a Massachusetts owner have to pay a contractor?
- On private projects whose prime contract is $3 million or more, the owner has 15 days to approve or reject a pay application in writing and 45 days after approval to pay; an application not rejected before payment is due counts as approved. Smaller private jobs follow the contract. On public building and public works contracts, cities and towns must pay a monthly estimate within 15 days and the state within 30, with interest if late.
- How fast must a Massachusetts contractor pay subcontractors?
- On private projects of $3 million or more, the contractor may take only 7 days longer than the owner to approve a sub's pay application, 22 days in all for a first-tier sub, and must pay within 45 days after approval; pay-when-paid clauses are void unless the sub failed to perform or the owner is insolvent. On competitively bid public jobs, the general contractor must pay each sub its share forthwith after being paid.
- When must a Massachusetts subcontractor record its notice of contract?
- By the earliest of 60 days after a notice of substantial completion is recorded, 90 days after a notice of termination, or 90 days after the last work on the project, and you must give the owner actual notice of the filing. A lower-tier sub or supplier should also send the general contractor a notice of identification by certified mail within 30 days of starting work, or its lien is limited to what is due or will become due on the first-tier subcontract.
- How much retainage can be held in Massachusetts?
- On private projects of $3 million or more, no more than 5% of any progress payment; you can apply for retainage 60 days after substantial completion, and it must be paid within 30 days of the application. Public building and public works contracts also cap retention at 5% of each periodic payment, and smaller private jobs have no statutory cap.
- Is there a limit on home-improvement deposits in Massachusetts?
- Yes. A deposit required before work starts may not exceed one-third of the total contract price or, if greater, the actual cost of special-order or custom materials that must be ordered in advance, and final payment cannot be demanded until the work is complete.
- Can a Massachusetts roofer handle a homeowner's insurance claim?
- Not for pay without a public insurance adjuster license; unlicensed adjusting carries fines of up to $10,000. Padding an estimate or invoice to hide a waived deductible can be prosecuted as insurance fraud, punishable by up to 5 years in state prison.
- Can a Massachusetts homeowner cancel a home improvement contract?
- Yes. A contract signed away from the contractor's place of business can be canceled until midnight of the third business day after signing, and the contractor must refund payments within 10 business days of receiving the cancellation notice.
- Do Massachusetts lien rules differ for home jobs?
- No separate deadlines apply: a contractor on a home job records a notice of contract and a statement of the amount due on the same schedule as on any other job. The lien rests on a written contract with the owner, which the Home Improvement Contractor law requires for jobs over $1,000 anyway.
Get matched to working capital
Answer a few questions in about 2 minutes and get matched to your best-fit option. Zero upfront fees. Checking won't impact your credit.
See what I qualify for →Sources
- M.G.L. c. 149, § 29F
- M.G.L. c. 30, §§ 39K, 39G
- M.G.L. c. 149, § 29E
- M.G.L. c. 254, §§ 2, 5, 8, 11
- M.G.L. c. 254, §§ 4, 8
- M.G.L. c. 142A, § 2(a)(6)
- M.G.L. c. 175, §§ 162, 172; c. 266, § 111A
- M.G.L. c. 140D, § 2(a); no commercial financing disclosure law enacted
- SBA Office of Advocacy, 2025 Massachusetts profile
- SBA district offices serving Massachusetts
Other states
Not legal advice. This page summarizes Massachusetts statutes as they read on November 19, 2026, for general information. Deadlines depend on the contract, the type of project, and any later amendments. Confirm a deadline with a Massachusetts construction attorney before you rely on it.
Disclaimer. WithFunded and Big Think Capital are a financing marketplace; we are not the direct lender and do not guarantee funding, approval, rates, or terms. Everything on this page is a representative example only — not an offer or a commitment to lend, and not financial advice. Actual rates, fees, payments, and terms are set by the funding lender and depend on your business, credit, and the product. Where required by state law, the lender provides cost-of-financing disclosures before any agreement is signed.